Getting Started - 3.5 - C240

Installing your C240 Clocking Terminal

You Will Need:

  • Your C240 Clocking Terminal, backplate, and the supplied connecting cables
  • The 4 rawl plugs, 4 long screws, and 1 grub screw that came inside the box with your C240 Clocking Terminal
  • A drill with an 8mm drill bit
  • A phillips head screwdriver
  • You may also need a 30mm circle saw (minimum size) depending on the wall the Clocking Terminal will be mounted to. 
  • Some customers opt to mount the Clocking Terminal on an IP65 Rated Box for ease of installation and access, though this is not essential. 

If you'd like to print this page for reference you can do so using the printer icon on the to right of the page.

1
Using the backplate as a guide, drill three holes in the mounting wall at a height of approximately 1.3 meters
2
Insert the 3   rawl plugs, one in each hole
3
Screw the backplate in place using the 3  long screws
4
Using the 30mm circle saw, make a hole at least 30mm across to allow all connecting cables to be fed through. Ensure they are also accessible from the other side
5
Feed the connecting cables through and connect them to the Clocking Terminal. The Power and Network cables should be connected as a minimum.
6
Mount the Clocking Terminal on the backplate
7
Secure the underside of the Clocking Terminal to the backplate using the 2  grub screws 

8
The Clocking Terminal can now be powered on 


Back to the Top

Did this answer your question? Thanks for the feedback There was a problem submitting your feedback. Please try again later.